Update 07.11.2024

  • It looks like they will be finished a had of schedule!
  • We will be back up and running tomorrow and all orders will ship between Monday-Wednesday.

Update: 07.10.2024

  • Tree cutting crews have arrived and they stated they’ll be done today.  So electric company will be able to do their part Thursday/Friday.

Update: 07.08.2024

  • We finally got an update from utility company.  All trees have been removed and power will be restored between Thursday July 11 and Monday July 15.  At this time all bulk and sewing operations will resume.
  • We thank everyone for your patience!

Update 07.05.2024

  • Power has been out for last 2 days due to storm damage covering about 2-3 blocks.  Because of this Bulk Herbal orders and Sewing Orders are on hold until power is restored.

Update 07.02.2024

  • Major storm passed through Chicago-land. Knocked down trees and power lines. Intermediate power at our packing/sewing facility.  We will keep everyone updated.